>I wanted to give you a heads-up on a logistical aspect of the pipeline
>survey this September. Since I sent you the survey budget on March 4,
>2005, it has become necessary to add alternate survey team members to
>assure that we have the required two person dive team this Fall. Persons
>diving on the project will all have participated in previous underwater
>surveys, be qualified for the data collection and will be thoroughly
>trained for the specific requirements of the project. This will not
>affect the cost of the survey but I wanted to secure your approval prior
>to proceeding with the sampling plan work and getting a commitment from my
>team members.
>
>Thanks,
>
>Phil
>
>
>At 01:05 PM3/30/2005-0800, you wrote:
>>Hi Phil,
>>
>>At the March 28, 2005 MCCSD Board Meeting, the Board approved the outfall
>>budget. Please proceed with preparation of the survey plan and schedule.
>>
>>Mike Kelley
************************************************************************